13.104.1 - Enhanced Durability
-
Capillary Break. A capillary break and vapor retarder shall be installed under the concrete slabs in accordance with ICC IBC Sections 1907, excluding exception #3 and 1805.2.1.
- Required Documentation:
Plans/specifications AND scope of work(s) detailing how requirement has been met. Photo(s) showing installation. Report from certified professional when the building code exceptions are used.
- Required Documentation:
-
Foundation drainage. Where required by the ICC IBC for habitable and usable spaces below grade, exterior drain tile is installed.
- Required Documentation:
Plans showing exterior drain tile for foundation, if applicable. Photo(s) showing installation.
- Required Documentation:
-
Dampproof walls. Walls that retain earth, and encloses interior space are required to be dampproof per ICC IBC Section 1805.
- Required Documentation:
Plans/specifications showing damp-proofing.
- Required Documentation:
-
Water-resistive barrier. Where required by the ICC IBC, a water-resistive barrier and/or drainage plane system is installed behind exterior cladding.
- Required Documentation:
Plans, specification, or scope of work showing WRB or drainage plane.
- Required Documentation:
-
Flashing. Flashing is provided as follows to minimize water entry into wall and roof assemblies and to direct water to exterior surfaces or exterior water-resistive barriers for drainage. Flashing details are provided in the construction documents and are in accordance with the fenestration manufacturer’s instructions, the flashing manufacturer’s instructions, or as detailed by a registered design professional.
Flashing is installed at the following locations, as applicable unless in conflict with manufacturer’s installation instructions:
-
Around exterior fenestrations, skylights, and doors
- At roof valleys
-
At all building-to-deck, -balcony, -porch, and -stair intersections
-
At roof-to-wall intersections, at roof-to-chimney intersections, at wall-to-chimney intersections, and at parapets
-
At ends of and under masonry, wood, or metal copings and sills
-
Above projecting wood trim
-
At built-in roof gutters, and
-
Drip edge is installed at eave and rake edges
-
Window and door head and jamb flashing is either self-adhered or liquid applied
-
Flashing is installed at exterior windows and doors
-
Through-wall flashing is installed at transitions between wall cladding materials or wall construction types
-
Flashing is installed at the expansion joint in stucco walls
- Required Documentation:
Plans/construction documents showing flashing details at all required locations.
- Required Documentation:
-
-
Tile backing materials. Tile backing materials installed under tiled surfaces in wet areas are in accordance with ASTM C1178, C1278, C1288, or C1325. Tile shall not be installed over paper-faced gypsum board in wet areas.
- Required Documentation:
Manufacturer’s literature/specification/labeling showing ASTM or other compliance. Plans/specifications and scope of work showing installation.
- Required Documentation:
-
Ice barrier. In areas where there has been a history of ice forming along the eaves causing a backup of water, an ice barrier is installed in accordance with the ICC IBC at roof eaves of pitched roofs and extends a minimum of 24 inches (610 mm) inside the exterior wall line of the building.
- Required Documentation:
Plans showing ice barrier.
- Required Documentation:
-
Architectural features. Architectural features that increase the potential for water intrusion are avoided, and must comply with the following:
-
Horizontal ledgers are sloped away to provide gravity drainage as appropriate for the application.
-
No roof configurations that create horizontal valleys in roof design, unless directed to a drain on a flat roof.
-
No recessed windows and architectural features that trap water on horizontal surfaces
-
-
Moisture control measures. Moisture control measures for newly installed materials are in accordance with the following:
-
Building materials with visible mold are not installed or are cleaned or encapsulated prior to concealment and closing
-
Insulation in cavities is dry in accordance with manufacturer’s installation instructions when enclosed (e.g., with drywall)
-
13.104.2 - Construction material and waste management plan
A written construction waste management plan is posted at the jobsite, and implemented.
Required Documentation
Review construction waste management plan.
13.104.3 - Core and shell material selection
The core and shell of the non-residential portion of the building must contain similar green material selections of the residential portion of the building, and must comply with the additional provisions of this section.
-
Material selection. At least six of these sections must be met from the following:
- See corresponding Chapter 6 practice.
13.104.4 - Recycling and composting
A readily accessible space(s) adequate to accommodate the recycling and composting containers for materials accepted in local recycling/composting programs is provided and identified on the floorplan.
Required Documentation
Plan review.