(1-2 points)
Intent
To encourage the design and construction of energy-efficient buildings that reduce air, water, and land pollution and adverse environmental effects from energy production and consumption.
Requirements
The requirements apply to 90% of the total building floor area (rounded up to the next whole building) of all nonresidential buildings, mixed-use buildings, and multiunit residential buildings four stories or more constructed as part of the project or undergoing major renovations as part of the project. Each counted building must comply with one of the following efficiency options.
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Option 1. Whole-building energy simulation (1–2 points)
New buildings must demonstrate an average percentage improvement of 12% (1 point) or 20% (2 points) over ANSI/ASHRAE/IESNA Standard 90.1–2010, with errata. Buildings undergoing major renovations as part of the project must demonstrate an average percentage improvement of 10% (1 point) or 18% (2 points). Core and shell buildings must demonstrate an average percentage improvement of 11% (1 point) or 15% (2 points). To determine percentage improvement, follow the method outlined in GIB Prerequisite Minimum Building Energy Performance.OR
Option 2. Prescriptive compliance: ASHRAE 50% Advanced Energy Design Guide (2 points)
To be eligible for Option 2, project must comply with all of requirements of Option 2 in GIB Prerequisite Minimum Building Energy Performance. AND Comply with the applicable recommendations and standards in Chapter 4, Design Strategies and Recommendations by Climate Zone, for the appropriate ASHRAE 50% Advanced Energy Design Guide and climate zone. For projects outside the U.S., consult ASHRAE/ASHRAE/IESNA Standard 90.1–2010, Appendixes B and D, to determine the appropriate climate zone. ASHRAE 50% Advanced Energy Design Guide for Small to Medium Office Buildings- Building envelope, opaque: roofs, walls, floors, slabs, doors, and continuous air barriers
- Building envelope, glazing: vertical fenestration
- Interior lighting, including daylighting and interior finishes
- Exterior lighting
- Plug loads, including equipment and controls
- Building envelope, opaque: roofs, walls, floors, slabs, doors, and vestibules
- Building envelope, glazing: fenestration - all orientations
- Interior lighting, excluding lighting power density for sales floor
- Additional interior lighting for sales floor
- Exterior lighting
- Plug loads, including equipment choices and controls
- Building envelope, opaque: roofs, walls, floors, slabs, and doors
- Building envelope, glazing: vertical fenestration
- Interior lighting, including daylighting and interior finishes
- Exterior lighting
- Plug loads, including equipment choices, controls, and kitchen equipment
- Building envelope, opaque: roofs, walls, floors, slabs, doors, vestibules, and continuous air barriers
- Building envelope, glazing: vertical fenestration
- Interior lighting, including daylighting (form or nonform driven) and interior finishes
- Exterior lighting
- Plug loads, including equipment choices, controls, and kitchen equipment
Pilot Alternatives Available
The following pilot alternative compliance path is available for this credit. See the pilot credit library for more information. EApc107 - Energy Performance Metering Path